A early look at the proposed design for the Mountains to Sound Greenway Trail connection crossing over Factoria Boulevard SE along I-90. Courtesy Photo

A early look at the proposed design for the Mountains to Sound Greenway Trail connection crossing over Factoria Boulevard SE along I-90. Courtesy Photo

Trail connection across Factoria Boulevard begins work in 2019

The Mountains to Sound Greenway Trail is the next big project for the city of Bellevue.

Bridging the 3.6-mile gap in Mountains to Sound Greenway Trail is the next big project for the city of Bellevue, and it’s planned to begin this year.

The Mountains to Sound Greenway trail runs from the Seattle waterfront all the way out to Ellensburg, providing an accessible route for pedestrians and bikers to travel through the Eastside. However, there is a 3.6-mile gap in the trail in the city of Bellevue from Interstate 405 to Southwest Lakemont Boulevard. City staff, along with partners at Mountains to Sound Greenway, have been working to connect the missing trail.

Project manager Chris Masek said the trail project will connect the gap through construction of new pathways. Planning for the work began in 2012, when the first planning study was conducted, he said.

The project is divided into three sections, the first traveling along Interstate 90 from I-405 to 132nd Avenue Southeast. The 3,000-foot long segment will feature a tunnel underneath the I-90/I-405 ramp, as well as a pedestrian and bicycle bridge above Factoria Boulevard to keep people away from the high-traffic area. Masek also said some alterations to the trail will also create an opportunity to expand traffic capacity at the intersection of Factoria Boulevard and I-90.

Increasing safety for pedestrians and bikers is one of the most important elements of the project. Keeping them separate with the new bridge will be a key element, he said.

“It provides a safe place where people could ride and walk that doesn’t exist today,” he said.

According to Masek, the project cost will come in at $17.7 million, the majority of which was funded by a $14 million grant from the Washington State Department of Transportation’s Connecting Washington funding program.

The city is tentatively planning to start construction this summer, but still is working on some property acquisitions along the project path. If construction begins this summer the city expects the first segment to be complete by Fall 2020, an 18-month construction period.

As for the remaining two segments, Masek said some design work has been done, but at this point the city and Mountains to Sound Greenway have not yet funded those construction costs.

More in News

Report: Only one use of excessive force upheld by Sheriff’s investigations in 2018

The Office of Law Enforcement Oversight has released its annual 2018 report.

Report: Only one use of excessive force upheld by Sheriff’s investigations in 2018

The Office of Law Enforcement Oversight has released its annual 2018 report.

Council checks in on status of proposed Sambica Activity Center rezone

The application for the rezoning was filed on Feb. 25.

Bellevue PD increases emphasis on child sex predators

Police say the number of crime-related tips have prompted the focus.

Bellevue suspect found dead in Seattle apartment

Police say Adam Gua died of a self-inflicted gunshot.

Eastside Pathways releases community report

The report was released late last month by the nonprofit.

The King County Courthouse. File photo
King County set to bring in tax-free housing funding

It’s set to reap $100 million over the next 20 years from state coffers.

Attendees take a closer look at the new Eastrail logo and tagline, “Let’s Connect” on July 20 in Redmond. Stephanie Quiroz/staff photo
East Rail Corridor is now Eastrail

Eastrail will be an uninterrupted 42-mile trail connected to Link light rail opening on the Eastside in 2023.

Most Read