Crews will begin working along Northeast 110th Street between Northeast Eighth and Northeast 10th streets next week as Puget Sound Energy installs new natural gas pipeline in the downtown area. - Fumiko Yarita / Bellevue Reporter
Fumiko Yarita / Bellevue Reporter
Crews will begin working along Northeast 110th Street between Northeast Eighth and Northeast 10th streets next week as Puget Sound Energy installs new natural gas pipeline in the downtown area.

PSE's natural gas pipeline work progresses through downtown Bellevue


September 12, 2008 · 9:43 AM

  • 0
  • Print Story
  • Letter/Editor

Puget Sound Energy’s work to install a new natural gas pipeline beneath 110th Avenue Northeast is pushing further south, with more lane closures and traffic disruption anticipated.

Crews are expected to begin the next section of work between Northeast Eighth and Northeast Sixth streets.

The northbound lanes in that section of 110th Avenue Northeast will be closed around the clock for approximately three weeks. Southbound lanes will remain open and access to businesses, including Bellevue City Hall, will be maintained.

Other sections of 110th Avenue will be closed in the northbound direction as PSE’s contractor for the work, Alaska Continental Pipeline, trenches its way south in the coming weeks.

A second crew working on the same pipeline project is trenching on 112th Avenue Southeast, between Main Street and Southeast Sixth Street. Lane closures will be required on 112th and delays are expected.

Both construction sites are part of PSE’s Bellevue Braids-Lake Hills Connector natural gas pipeline project. The utility is adding the 3.5 miles of new pipeline to accommodate projected growth downtown and to provide a backup for an existing line.

For additional information, including a detailed map, visit PSE’s website at www.pse.com/community/yourneighborhood/pages/CurrentProjects.aspx?tab=2&chapter=2.

All downtown work is scheduled for completion by Nov. 15. Installation work on the rest of the pipeline will wrap up by the end of 2008; repaving work will be finished in spring 2009.

Puget Sound Energy’s work to install a new natural gas pipeline beneath 110th Avenue Northeast is pushing further south, with more lane closures and traffic disruption anticipated.

Crews are expected to begin the next section of work between Northeast Eighth and Northeast Sixth streets.

The northbound lanes in that section of 110th Avenue Northeast will be closed around the clock for approximately three weeks. Southbound lanes will remain open and access to businesses, including Bellevue City Hall, will be maintained.

Other sections of 110th Avenue will be closed in the northbound direction as PSE’s contractor for the work, Alaska Continental Pipeline, trenches its way south in the coming weeks.

A second crew working on the same pipeline project is trenching on 112th Avenue Southeast, between Main Street and Southeast Sixth Street. Lane closures will be required on 112th and delays are expected.

Both construction sites are part of PSE’s Bellevue Braids-Lake Hills Connector natural gas pipeline project. The utility is adding the 3.5 miles of new pipeline to accommodate projected growth downtown and to provide a backup for an existing line.

For additional information, including a detailed map, visit PSE’s website at http://www.pse.com/community/yourneighborhood/pages/CurrentProjects.aspx?tab=2&chapter=2.

All downtown work is scheduled for completion by Nov. 15. Installation work on the rest of the pipeline will wrap up by the end of 2008; repaving work will be finished in spring 2009.

Comment on this story.

COMMENTING RULES: We encourage an open exchange of ideas in our online community, but we ask you to follow our guidelines for respecting community standards. In a nutshell, don't say anything you wouldn't want your mother to read.

So keep your comments:

  • Civil
  • Smart
  • On-topic
  • Free of profanity

We ask that all participants own their words by logging in with their Facebook account. It's a simple process that will take seconds and helps keep our comments free of trolls, cranks, and “drive-by” commenters. We reserve the right to remove comments from anyone using screen names, pseudonyms or false identities. Please see our FAQ if you have questions or concerns about using Facebook to comment.

blog comments powered by Disqus